King Abdulaziz International Airport (KAIA) Sea Water Desalination Plant
King Abdulaziz International Airport (KAIA) Sea Water Desalination Plant
Location:
King Abdulaziz International Airport, Jeddah
Capacity:
35,000m3/day
Technology:
Seawater Reverse Osmosis (SWRO)
Scope of Work:
Build Own Operate Transfer (BOOT) development, including financing, engineering, procurement, construction and operation and maintenance of a 30,000m3/day Reverse Osmosis (RO) desalination plant to be expanded to 35,000 m3/day after 7 years of operation. A 20-year O&M phase led by SETE Energy will follow construction.
SETE’s Role:
Lead developer, equity investor, engineering, procurement, construction and project management, lead operation and maintenance contractor
Schedule:
EPC: January 2007 June 2009
O&M:
June 2009 June 2029
Client / Offtaker:
General Authority for Civil Aviation